Thomas O. Price Service Center
Tucson, Arizona
The City of Tucson has a demonstrated commitment to the promotion
of sustainable development practices, and is considered a leader
in the area of energy efficiency. This case study will highlight
a city effort - the retrofit of an existing municipal building -
to practice and promote energy efficiency design principles and
technologies in this desert community of nearly 500,000 people.
The city's Department of Operations takes the lead in the design
of city facilities, and played this same role in bringing this project
to fruition. For additional information about the City of Tucson's
energy efficiency programs, visit
www.ci.tucson.az.us.
The Thomas O. Price Service Center Building One project was a
retrofit of an existing 23,400 sq. ft. office building. This one
story building houses 80 full-time employees in various City administration
roles.
Energy efficiency upgrades on the building began in 1995 with
a lighting retrofit. The upgrade cost was $31,300, with an annual
avoided electricity cost of $5,700, or a simple payback period of
5.5 years. In May 1999, occupancy sensors were installed throughout
the building at a cost of $3,000, with an estimated annual avoided
electricity cost of $375, or a simple payback period of 8.0 years.
By May 2001, several additional efficiency projects had been completed
at a cost of $128,200, including the addition of an energy management
and control system and the changeover of a constant volume dual
duct air handling system to a variable air volume system. With an
estimated avoided electricity cost of $22,400 per year, the simple
payback period of these efforts is 5.7 years.
A "cool roof" was added to Building One in June 2001, as part
of Tucson's Creating Cool Communities program, an effort to develop
mitigation strategies for offsetting the urban heat island effect.
Urban heat islands are a phenomenon affecting large urban centers.
They occur when urbanized areas accumulate greater amounts of heat
during the day than their rural surroundings, sometimes reaching
temperatures six to eight degrees hotter. Cities also retain the
increased temperatures throughout the night. Dark, heat absorbing
surfaces such as building roofs and parking lots contribute to this
effect, causing an increase in energy usage, energy costs, air pollution,
and greenhouse gas emissions. Building One was chosen as a cool
roof demonstration project because of its general setup and ease
of monitoring due to its ongoing participation in the U.S. EPA's
Energy Star Buildings program.

Building One's roof is about 28,000 sq. ft. in area, including
flashings. The vast majority of it is surfaced with a sturdy aluminum
foil over its low-slope, and a copper foil that has turned black
with time over the more steeply sloped sections. Although somewhat
reflective, bare metallic surfaces have low emissivity and therefore
retain high levels of heat. A white elastomeric top coating was
applied to the roof in June 2001.
Two methods were used to evaluate the energy savings listed below:
First, by looking directly at "raw" data from a week before and
a week after the cool roof was applied; and second, by adjusting
this raw data to account for weather and occupancy variations.
Table 1 compares pre-installation (May 7 - 13, 2001) to post-installation
(July 23 - 29, 2001) peak and average temperatures. These weeks
experienced similar weather conditions, and provide a good opportunity
for comparison. The cool roof reduces the black portion of the roof's
peak temperature by more than 70 degrees Fahrenheit, and the metal
portion's temperature is reduced by over 40 degrees Fahrenheit.
Table 1. Hot and Cool Roof Temperature Comparisons
| |
Hot Roof Surface (Regressed values) |
Cool Roof Surface (Actual values) |
Temperature Reduction |
| Peak Temperatures |
|
|
|
| Black Roof |
198°F |
120°F |
78°F |
| Metal Roof |
165°F |
119°F |
46°F |
| Avg. Temperatures |
|
|
|
| Black Roof |
102°F |
85°F |
17°F |
| Metal Roof |
95°F |
85°F |
10°F |
Table 2 provides estimates of the energy savings due to the cool
roof.
Table 2. Cooling Energy Savings Due to Cool Roof
| Weekdays Only |
Energy Use (MBtu) |
| Hot roof cooling energy use, regressed values
(May 7 - 13, 2001) |
37.8 |
| Cool roof cooling energy use, actual values
(July 23 - 29, 2001) |
19.4 |
| Savings |
18.4 |
| % savings |
48.7% |
The reductions in energy consumption in the building due to the
cool roof are quite outstanding. Nearly 50% cooling energy usage
reduction was seen after installation. This result is even more
impressive when taking into consideration that Building One had
been retrofitted with modern energy efficient lighting, mechanical
systems and building controls prior to the roof retrofit.
Avoided energy usage can be estimated at over 400 million BTUs
annually. This translates into an avoided energy cost of nearly
$4,000 annually. The cost of the new roof coating was $24,993; therefore,
the simple payback period is just over six years, and the rate of
return is 16%. The payback is moderately long in part because the
building was relatively efficient prior to the roof retrofit (see
Figure 1). In addition to the monetary savings, the reflective roof
coating eliminated several roof leaks and extended the life of the
existing roof.
Figure 1 shows the average monthly electricity use of the building
from 1990 through 2001. As a result of the series of efficiency
retrofits described above, including the cool roof, total electricity
use and cost declined from around 432,000 kWh and $38,600 per year
in the early 1990s to about 162,000kWh and $16,100 per year in 2001,
a reduction of more than 55 percent. During this time period the
building saw a substantial increase in occupants and office equipment,
most notably personal computers, making the savings even more impressive.
Note that the savings shown in Figure 1 only include the direct
building electric usage, as the heating hot water and cooling chilled
water come from an adjacent central plant. The utility bills for
the central plant have also decreased by over $23,000 annually since
1998.
Total energy efficiency upgrades performed on Building One cost
$187,500, and produce over $40,000 in annual energy cost savings,
well above the $32,500 estimate. Overall payback on the entire menu
of energy efficiency projects is therefore 4.7 years. Pollution
prevention is estimated at nearly 350 tons of CO2 equivalent annually.
Figure 1. Thomas O. Price Service Center Building One, Average
Monthly Electricity Use (kWh)

|